Expansion of WWTP in Cala Baeza, El Campello
Background
With the construction of 127 new homes in Cala Baeza (El Campello), an increase in wastewater is expected in the area. This situation required the expansion of the treatment unit to provide a solution to the volume of wastewater produced in the area. Prior to the project designed by BlueGold, there was a wastewater treatment plant for 100 m3.
In view of the conditions described above, the needs are as follows:
- guaranteeing sufficient capacity to allow adequate treatment of the water,
- reinforcing the capacity offered by the current system,
- under the premise that for space reasons, it must be a compact system.
Our solution
In order to offer a solution that provides efficiency and quality in the effluent, factors such as the space available for the installation and the quality required were taken into consideration. Likewise, issues that could affect the operation of the system, such as seasonality of use and variation of incoming flow, were also taken into account. Taking into account the variables described above, the best option was an MBR membrane bioreactor, a technology that allows us to implement the equipment in a reduced space but that offers great results, even under disparate operating conditions.
In order to expand the existing WWTP, given the quality required, the most appropriate solution was the Bioxirec | Membrane Biological Reactor (MBR) system, located in a self-supporting container that allows its deployment quickly and without the need for civil works.
Being integrated in a self-supporting container, from BlueGold’s facilities, the system was ready to be moved to the final location and offer the quality that the project required with a speed that met the needs.
PROJECT DETAILS
Location
Cala Baeza, El Campello
Customer
Cala Baeza, El Campello
Solution
Bioxirec : Membrane Biological Reactor (MBR)
Results
The right solution is the one that is able to deliver the expected results but is capable of being adapted to the particularities of the case. Therefore, at the express request of the municipality when the project was commissioned, a grease separator was included. Likewise, a continuous chlorine doser has been integrated to reinforce the already high capacity of the membranes to prevent the passage of microorganisms.
The result is an effluent with a quality water that guarantees the deactivation and elimination of the microorganisms present in the water.
Benefits
The design created for the project allows to obtain a debugging system with the following characteristics:

A compact system with a smaller membrane biological reactor and no secondary clarifier.

Higher sludge concentration (MLSS: 10-20 g/L) than conventional treatment (MLSS: 3-4 g/L).

Efficiency greater than 90% for suspended solids, BOD5 and pollutants
Need more information?
Our professionals will guide you through the entire process of selecting water treatment equipment. They will always tell you the particularities of the different products and the choice that best suits your needs.
CERTIFICATIONS
Different accreditations certify our commitment to quality and service. Therefore, achieving a quality standard is part of our essence, which results, consequently, in making available to our customers the excellence of a professional and specialized service.
Referencias de clientes
Blue Gold trabaja desde 2004 en soluciones para tratamiento de agua, instalaciones químicas, automatización y sistemas industriales.
Las centrales de ciclo combinado de Naturgy han contratado los servicios de la empresa Blue Gold con excelentes resultados en las mejoras de tratamiento de agua y en servicios de monitorización de vapor.
Blue Gold lleva trabajando desde el año 2006 con nuestra central de Ciclo Combinado de Tarragona, suministrando consultoría de Ingeniería, equipos y trabajos de instalación y mano de obra, con gran éxito.
El equipo de Blue Gold y su personal de dirección de obra trabajan con altos estándares de calidad y ejecutan sus trabajos de forma responsable, con una buena gestión de la seguridad y la salud.
Latest news
Engineering is a field where different sectors and professionals interact with the same objective: to provide society with technology that benefits us all. In this framework of common good, we echo those news that are relevant to the general purpose of an engineering at the service of a sustainable future.
Más de 20 años
de experiencia en el desarrollo de proyectos de ingeniería nos avalan para poder ofrecer soluciones tecnológicas que den respuestas técnicas a: tratamiento de agua
e instalaciones eléctricas
o químicas.
Contacto
Carrer de Gabriel Miro, 11, 03560 El Campello, Alicante
Lun.-Vie. 8:00 - 19:00